A June tender describes 850 m of separated walking and cycling space
The separation project has moved into procurement, but the retrieved records do not confirm where crews or barriers are present today.
A June tender describes 850 m of separated walking and cycling space. That differs from May’s 600 m report, and no official current-access schedule was found.
Unknown at the work site.
The tender was posted in June and allows 150 days from commencement. A tender period does not prove that crews are on site, and the retrieved official records do not provide a reliable commencement date or a current access plan.
Check the present signs before using this section. Do not rely on the May target date as proof that construction started, and do not assume the whole Suyeong River line is closed.
Potentially useful, currently uncertain.
If completed as tendered, the separated layout should reduce conflict on a connector people already use. During construction, the practical issue is local barriers or narrowing. Their current position is not published.
May report area: Banyeo-dong, Haeundae-gu, Busan. Tender address: around Suyeonggangbyeon-daero 473 / Jae-song-dong 1265. May report: Wondong IC–Centum Daelim Apartment area, 600 m long and 6–8 m wide. June tender: around Suyeonggangbyeon-daero 473, 850 m long and 4–5 m wide. Tender duration: 150 days from commencement. Current closure, detour and rideability: not confirmed by the retrieved sources.
The project reached an official tender. Its published scope changed along the way.
This is the kind of small project that can matter more than it sounds. A short shared stretch with walkers and bikes squeezed together can ruin the flow of a much longer river ride.
Free Busan bike checks on September 30 and October 28 include rear lights
Bring a bicycle to the Oncheonjang Station public rental point on September 30 or October 28 for a free basic check

Finishing 7 Bridges on a folding bike
Great weather, a great route, and good people and atmosphere, but challenging cutoff times for many riders on non-road bikes