Galmaetgil audit finds many location-plate QR failures
Only 52 of 272 checked national point-location plate QR codes worked normally
Three Dongnae contracts list work through late November or early December
Check signs around Myeongnyun and between Big Tree Rest Area and Suyeon Bridge. The new Suyeong River contract does not publish a precise work limit.
Three Dongnae contracts list work through late November or early December. Expect local work zones, but no official source shows either riverside route closed end to end.
| Section | Published scope | Contracted works period |
|---|---|---|
| Suyeong River, Dongnae section | Walking and bicycle-path maintenance; the register does not identify the exact work limit | September 15–November 23 |
| Oncheoncheon, Big Tree Rest Area to around Suyeon Bridge | 900 m of walking/bicycle-path work, including 0.8 m widening | August 24–November 21 |
| Oncheoncheon, around Myeongnyun Station | 450 m bicycle-path project, 3 m wide | September 4–December 2 |
These are contract periods. They do not mean every metre is blocked for every day of the contract, and the listed completion dates do not confirm reopening by themselves.
Expect local narrowing, barriers, or short diversions where crews are working. Check the sign at the entrance instead of assuming the entire river path is unavailable.
The two Oncheoncheon contracts name their general areas. The Suyeong River contract lists September 15 as the start date, but its public page does not identify the affected Dongnae segment. No official day-by-day access schedule or detour map was found for these three projects.
Current rideability is therefore condition-dependent and not confirmed for every section. If a barrier is in place, follow any marked diversion rather than squeezing through the work zone.
These are separate district projects, not one coordinated river closure. Haeundae’s Banyeo Suyeong River separation project has a June tender but no confirmed current access plan. The Jangjeon/Guseo Oncheoncheon work had a signed period ending September 1, with no reopening confirmation found.
Neither item changes the limits or dates of the three Dongnae contracts above. Treat each site separately and check its current signs before changing a ride.
Several work sites. No river-wide closure notice.
Dongnae’s contract register confirms three current walking or bicycle-path projects along the Suyeong River and Oncheoncheon. The contracts run into late November and early December, but they do not say that either riverside route is closed from end to end.
Galmaetgil audit finds many location-plate QR failures
Only 52 of 272 checked national point-location plate QR codes worked normally
Free Busan beginner bike course opens for women aged 40–65
Women aged 40–65 who cannot yet ride a two-wheel bicycle can apply through September 27 for eight free Wednesday lessons at Spo1 Park